Action Development Project

Within the scope of the contract signed with ANT YAPI for the Office and Hotel Project Diaphragm Wall and Top-Down Bored Pile Works; 6,000 m2 of Diaphragm Wall and 2,000 m of Bored Pile works have been completed. The project is located in Presnenskiy Region in Moscow.

Project Description

Action Development Project

  • Engineering

Project Features

Client
ANT YAPI
Key Quantities
Diaphragm Wall 6,000 m2
Bored Pile 2,000 m
Project Duration
Start Date 17.06.2018
Finish Date 26.09.2018
Duration 3 Months

Location

Moscow, Russia

 

 