Çanakkale 1915 Bridge Project / European Anchor Block Excavation

The contract of the Çanakkale 1915 Bridge European Anchor Block Excavation Works has been signed with DLSY JV. Within the scope of the project which consists of Kınalı-Tekirdağ-Çanakkale-Savaştepe Highway; there are 5,400 m of Secant Pile; 9,500 m of Rock Bolt, Shotcrete, Excavation and Dewatering works.

Project Description

Çanakkale 1915 Bridge Project / European Anchor Block Excavation

  • Engineering

Project Features

Client
DLSY JV.
Key Quantities

Secant Pile 5,500 m
Rocks Bolt 10,000 m

Project Duration

Start Date 17.05.2018
Finish Date 10.10.2018
Duration 5 Month

Location

Canakkale, Turkey

 

 