Geotechnical works within the scope of the ICITY Towers Project continue in accordance with the work schedule. After the completion of the execution of foundation piles under the first skyscraper within the project, which was started on February 20, 2021, the execution of the shoring system was commenced. The shoring system composed of pipe pile and Berliner wall installation works, were completed on August 10, 2021. After the completion of pipe pile and Berliner wall, the excavation of the shoring pit was carried out. In July, pipe support system and dewatering systems construction were started. By the end of August, 60% of the bored piles, 30% of the pipe piles and 30% of the excavation works have been completed. The remaining works within the project are planned to be completed by April 2022.