The contract for the Top-Down Pile works within the scope of the underground mall project, located in Paveletskaya, one of the busiest centres of Moscow, was signed with Ant Yapı on September 11, 2019. The project includes 4,700 m of Top-Down Piles with a diameter of 1,200 mm. Installations were started on September 1, 2019 and completed on January 27, 2020.

Project Description

Paveletskaya Underground Mall Project

  • Engineering

Project Features

Client
Ant Yapı
Key Quantities
Top-Down Pile 4,700 m
Project Duration
Start Date 01.09.2019
Finish Date 27.01.2020
Duration 5 Months

Location

Arabia

 

 