A tunnel at the intersection of Tahliah Street and Madinah road in Jeddah was decided to be built in order to reduce the heavy traffic. The soil improvement works comprise of the design and implementation of bottom plug by means of tangent jet grouting to form an impervious blanket. The purpose of bottom plug is to minimize the ground water for the underpass excavation and protection of the existing buildings and foundations of the Madinah Road Bridge. Within the scope of the project, the construction of 12,000 m of Jet Grout was designed by Kasktaş. The contract was signed with Advanced Construction Company on September 5, 2019.

Project Description

Improvement of Tahliah Madinah Intersection Underpass

  • Engineering

Project Features

Client
Advanced Construction Company
Key Quantities
Jet Grout12,000 m
Project Duration
Start Date12.12.2019
Finish Date01.01.2021
Duration13 months

 

Location

Arabia
[wpgmappity id=”2″]

 

 

Related Projects

MBE METRO PROJECT TOKİ STATION SHORING WORKS

MBE METRO PROJECT TOKİ STATION SHORING WORKS

Completed Projects Deep Excavations Deep Foundations...
FERRERO DÜZCE NUT CRACKING AND SELECTION FACILITY

FERRERO DÜZCE NUT CRACKING AND SELECTION FACILITY

Completed Projects Deep Foundations Soil Improvement...
CSS METRO PROJECT S21B SWITCH STRUCTURE

CSS METRO PROJECT S21B SWITCH STRUCTURE

Completed Projects Deep Excavations Turkey
ICITY TOWERS PROJECT

ICITY TOWERS PROJECT

Completed Projects Deep Excavations Deep Foundations...