Jabal Al Ka Aba Phase 3 Slope Stabilization Works

The contract was signed with Abdul Latif Jameel Real Estate Investment for the Jabal Al Ka’aba Phase-3 Project, located in Mecca. Within the scope of the project, there are 3,100 m of Rock Bolt and 2,125 m2 of Shotcrete works.

Slope stability works were started on March 10, 2020. Due to the Covid-19 epidemic, curfew was declared in Mecca. Therefore, the work was suspended and demobilized from the work site. After the field is prepared for working, it will be mobilized again and the construction is planned to completed on June 1, 2021.

Project Description

Improvement of Tahliah Madinah Intersection Underpass

  • Engineering

Project Features

Client
Abdul Latif Jameel Real Estate Investment
Key Quantities
Rock Bolt 3,100 m
Shotcrete 2,125 m2
Project Duration
Start Date 10.03.2020
Finish Date Current
Duration

 

Location

Arabia

 

 

Related Projects

Masar Project ST 06 Bored Pile Works

Masar Project ST...

Completed Projects Deep...
BMT Container Terminal

BMT Container Terminal

Basrah Current Projects...
Nador Port Project

Nador Port Project

Current Projects Deep...
Masar Project Package A Shoring Works

Masar Project Package...

Asia Current Projects...