The contract for the End of Stretch 4 Shoring Works within the scope of the King Abdulaziz Road Project was signed with Nesma & Partners Contracting on May 21, 2019. Due to the project’s proximity to the Harem and the location of the Zamzam Water flow line within the project site, the concrete was requested not to reach the groundwater level, and for this reason, the Berliner Walled Shoring project was designed by Kasktaş. Within the project, there are 2,450 m of Anchor and 700 m2 of Berliner Wall. The construction was started on June 24 and completed on September 15, 2019.
Project Description
Kral Abdülaziz Road Project End of Stretch 4
- Engineering
Project Features
Client
Nesma % partners Contracting
Key Quantities
Anchor | 2,450 m |
Berliner Wall | 700 m2 |
Project Duration
Start Date | 24.06.2019 |
Finish Date | 15.09.2019 |
Duration | 3 Months |
Location
Arabia