Within the scope of the Satellite Desalination Plants Construction Project, Saudi Arabian Ministry of Environment aims to build 8 number of desalination plants on the shoreline of Red Sea. The contract for the construction of Secant Piles within the scope of the Haql Plant was signed with Peaks Construction & Maintenance Co. Ltd. on October 1, 2019. There is 2,200 m of Secant Pile within the scope of the project. The installation was started on October 1 and completed on November 20, 2019. Dewatering works, which were started on December 15, 2019, were completed on April 5, 2020.
Project Description
Satellite Desalination Plants Construction Project Haql Plant
- Engineering
Project Features
Client
El Seif Engineering
Key Quantities
Secant Pile | 2,200 m |
Dewatering Well | 8 Nos |
Project Duration
Start Date | 01.10.2019 |
Finish Date | 05.04.2020 |
Duration | 7 Months |
Location
Arabia