The installation of preliminary test piles at the Filicity Residential construction foundation pile project in Moscow was completed in April, 2018.
Within the scope of the project there are 465 no. of bored pile with a diameter of 1200 mm and a length of 12 m. Diaphragm wall is selected as the most suitable shoring system in order to excavate construction pit. The final excavation level is -13 m.
Since the diaphragm wall and bored pile construction are planned to be executed simultaneously, the piling works will be carried out from the temporary working platform, therefore the total pile drilling length will be 25 m. The exact quantities of the bored piling works will be verified and finalized based on the results of the pile tests.