A complex of two skyscrapers in the Moscow City Region is planned to be built. The test piles of the ICITY Tower Project were previously executed and tested by Kasktaş. Later, a subcontract for the execution of bored piling, soil improvement and excavation works, was signed with MR Group as of July 1, 2020. There are 10.000 m of Pipe Pile, 13.300 m of Bored Pile, 9.000 m of Jet Grout, 12.500 m2 of Berliner Wall and Excavation Works within the scope of the Project.
The construction was started on February 20, 2021. A total of 1.200 m of Pipe Piling and 2.200 m of Bored Piling works have been completed by the end of April 2021. All works within the scope of the project are planned to be completed by December 10, 2021.