All shoring works within the scope of the Nador West Med Port Project, which is under construction in the north of Morocco, was completed.
The executions in the project, which is divided into Service Quay and RoRo regions, was started on December 17, 2020. A total of 18,000 m3 of diaphragm walls with depths ranging from 19 to 38 m and a total of 6,000 m3 of barrette piles with depths ranging from 8 to 16 m were completed, and all works within the scope of the project were accomplished as of December 24, 2021.