The contract for Soil Nail and Shotcrete works which prevent the deformation that occurs during the excavation of 700 mm clean water line feeding the Harem within the scope of the King Abdulaziz Road Project was signed with Nesma & Partners Contracting on July 9, 2019. The project includes 800 m of Soil Nail; 3,200 m2 of Shotcrete; 3,700 m of Anchor and 800 m2 of Berliner Wall. The construction was started on July 1, 2019. Due to the restrictions introduced after Covid-19 epidemic and the transition to summer working hours, the project was completed on January 1, 2021.