The contract was signed on September 19, 2020 with Mafaheem Al-E’mar for the Tower Construction Shoring Works within the scope of the National Company Building for Mechanical System Project, located in Riyadh. The contract consists of Secant Pile and Anchor works.

In the project, which started as of October 2020; 3,600 m of secant pile has been completed by the end of 2020. The remaining secant piles are predicted to be completed in February 2021. After the completion of piling works, anchor installation will be commenced and is planned to be completed by March 2021.

Project Description

NCMS Tower Shoring Works

  • Engineering

Project Features

Client
Mafaheem Al‐E’mar
Key Quantities
Anchor 5,600 m
Project Duration
Start Date 06.10.2020
Finish Date Devam Ediyor
Duration

 

Location

Arabia

 

 

Related Projects

Masar Project ST 06 Bored Pile Works

Masar Project ST...

Completed Projects Deep...
BMT Container Terminal

BMT Container Terminal

Basrah Current Projects...
Nador Port Project

Nador Port Project

Current Projects Deep...
Masar Project Package A Shoring Works

Masar Project Package...

Asia Current Projects...