Two towers are planned to be built for the National Company for Mechanical System in Riyadh, Saudi Arabia. The contract covering the shoring works for the safe excavation pit of the foundations of the towers was signed with Mafaheem Al-E’mar on September 19, 2020. The shoring project, which was designed by Kasktaş, includes 8,000 m of Secant Pile and 5,600 m of Anchor works.
Within the scope of the project, after the secant pile applications were completed, the head beam was constructed. Later, the excavation works were started. Anchor works were carried out simultaneously with the excavation. Following the completion of the excavation, the third-row anchor construction was accomplished, and the project was successfully completed.
Project Description
NCMS Tower Shoring Works
- Engineering
Project Features
Client
Mafaheem Al‐E’mar
Key Quantities
Anchor | 5,600 m |
Secant Pile | 8,000 m |
Project Duration
Start Date | 06.10.2020 |
Finish Date | 01.10.2021 |
Duration | 12 months |
Location
Arabia