Diaphragm wall with a thickness of 600 mm and 1,000 mm diameter top-down bored pile construction works were successfully completed within the scope of the Smolenskaya Multi-Purpose Public Building Project; which consists of a 12-storey shopping center and office buildings. A total of 6,200 m2 of diaphragm wall and 2,000 m of top-down bores piles were installed.

Project Description

Multi-Purpose Public Buildings in Smolenskaya, Moscow

  • Engineering

Project Features

Client
ZAO Prokons
Key Quantities
Diaphragm Wall6,200 m2
Top Down Pile2,000 m
Project Duration
Start Date01.05.2011
Finish Date01.12.2011
Duration7 Months

Location

Moscow, Russian Federation
[wpgmappity id=»95″]

 

 

Gallery

Related Projects

ICITY TOWERS PROJECT

ICITY TOWERS PROJECT

Completed Projects Deep Excavations Deep Foundations...
ПРОЕКТ ЖИЛОЙ КОМПЛЕКС СИМВОЛ

ПРОЕКТ ЖИЛОЙ КОМПЛЕКС СИМВОЛ

Asia Completed Projects Deep Foundations Russian Federation
КУТУЗОВСКИЙ КОМПЛЕКС СТРОИТЕЛЬСТВА ЭТАП 1 И 2

КУТУЗОВСКИЙ КОМПЛЕКС СТРОИТЕЛЬСТВА...

Asia Completed Projects Deep Excavations Deep Foundations...
КОМПЛЕКС СЕРДЦЕ СТОЛИЦЫ, ЭТАП 4, ПРОЕКТ

КОМПЛЕКС СЕРДЦЕ СТОЛИЦЫ, ЭТАП 4, ПРОЕКТ

Asia Completed Projects Deep Excavations Deep Foundations...