Within the scope of Izmit Tüpraş Refinery Upgrading Projects, soil improvement works were completed under 5 different Employers. Between 2011 and 2012, a total of 162,000 m Jet Grout, 21,500 m Foundation Piles and 3,800 m Barette Piles were installed in five separate sub-contracts.
Project Description
İzmit Tüpraş Refinery Upgrading Projects (2011-2012)
- Engineering
Project Features
Client
Ark Construction, Tekfen Construction, Gemont, Çimtaş, Artaş Construction
Key Quantities
Ark Construction | Tekfen Construction | ||
Foundation Pile | 3,500 m | Foundation Pile | 8,100 m |
Jet Grout | 132,000 m | Jet Grout | 30,000 m |
Gemont | Barette Pile | 3,800 m | |
Foundation Pile | 6,200 m | Çimtaş |
|
Artaş Construction | |||
Foundation Pile | 2,500 m | Foundation Pile | 1,200 m |
Project Duration
Start Date | 01.09.2011 |
Finish Date | 01.06.2012 |
Duration | 9 Months |
Location
Kocaeli, Turkey