• 001

The project, located within King Abdul Aziz Airport area, includes the expansion of existing domestic and international passenger terminals. Bored pile installation works were completed in two different sites, the north and south terminals.

Project Description

Jeddah King Abdul Aziz International Airport Expansion and Renovation of Passenger Terminals Project

  • Engineering

Project Features

Client
Saudi Binladin Group
Key Quantities
Bored Pile 3,467  m
Project Duration
Start Date 01.03.2007
Finish Date 01.07.2007
Duration 4 Months

Location

Jeddah, Saudi Arabia

 

 