King Abdulaziz Roadway Project, whose construction is ongoing in the Mecca, Saudi Arabia, consists of the construction of a new bridge that is connected to the Jeddah-Mecca Motorway. Within the scope of the project; 300 m of Bored Pile with Ø 120 cm diameter has been completed by August 2018. Besides; 1,050 tons of loading test has been applied to the working piles.

Project Description

King Abdulaziz Roadway Project

  • Engineering

Project Features

Client
NESMA
Key Quantities
Bored Pile 300 m
Project Duration
Start Date 11.06.2018
Finish Date 16.09.2018
Duration 3 Months

Location

Mecca, S.Arabia

 

 

Gallery