Krasnopresnenskaya Project

Within the scope of the contract signed with OOO BOES CONSTRUCTION for the Multifunctional Complex Project Bored Pile Works; 16,500 m of Bored Pile with Ø 88-100 cm diameters has been completed. The project is located in the Krasnopresnenskaya Region in Moscow.

Project Description

Krasnopresnenskaya Project

  • Engineering

Project Features

Client
OOO BOES CONSTRUCTION
Key Quantities
Bored Pile 17,000 m
Project Duration
Start Date 11.01.2017
Finish Date 06.04.2018
Duration 15 Months

Location

Moscow, Russia

 

 