NEF 163 and NEF 11 Multi Functional Residence and Office Projects were completed in 2011. Within the scope of NEF 163 4,400 m Anchors and 350 m Soil Nails were completed.  Within the content of NEF 11 Project 5,500 m of Bored Pile; 6,400 m of Foundation Bored Pile; 5,300 m of Anchor and 26,000 m of Jet Grout were installed.

A total of 5,700 m2 Diaphragm Wall; 5,000 m Anchor; 13,000 m Bored Pile and 22,500 m Jet Grout were completed within the scope of Nef 03 Kagithane Residence and Office Project in 2014.

  • NEF 163 — 2011
  • NEF 11 — 2011
  • NEF 03 — 2014

Project Description

NEF 163

Project Features

Client
Global Gayrimenkul
Key Quantities
Anchor4,400 m
Soil Nail350 m
Project Duration
Start Date01.03.2010
Finish Date01.06.2010
Duration4 Months

Location

Istanbul, Turkey

Project Description

NEF 11

Project Features

Client
Global Gayrimenkul
Key Quantities
Bored Pile5,500 m
Foundation Pile6,400 m
Anchor5,300 m
Jet Grout26,000 m
Project Duration
Start Date01.06.2010
Finish Date01.08.2010
Duration5 Months

Location

Istanbul, Turkey

Project Description

NEF 03

Project Features

Client
NEF
Key Quantities
Diaphragm Wall5,700 m2
Anchor5,000 m
Bored Pile13,000 m
Jet Grout22,335 m
Project Duration
Start Date01.02.2014
Finish Date01.11.2014
Duration8 Months

Location

Istanbul, Turkey

 

 

Gallery

Related Projects

FERRERO ЗАВОД ПО ДРОБЛЕНИЮ И СОРТИРОВКЕ ФУНДУКА г. ДЮЗДЖЕ

FERRERO ЗАВОД...

Completed Projects Deep...
CSS ПРОЕКТ МЕТРО НОЖНИЧНАЯ КОНСТРУКЦИЯ S21B

CSS ПРОЕКТ...

Completed Projects Deep...
1915 Canakkale Bridge European Approach Viaduct Ground Treatment And Pile Works

1915 Canakkale Bridge...

Completed Projects Deep...
Üsküdar Underground Car Park

Üsküdar Underground...

Completed Projects Deep...