• 001

In this project, where the employer is Sedef Gemi İnşaat, a total of 168,000 m Jet Grout Column and 35,000 m Bored Pile were installed in Tuzla Sedef Shipyard between 2005-2008.

Project Description

Tuzla Sedef Shipyard

  • Engineering

Project Features

Client
Sedef Gemi İnşaat
Key Quantities
Bored Pile35,000 m
Jet Grout Column168,000 m
Project Duration
Start Date01.04.2005
Finish Date01.12.2008
Duration45 Months

Location

Istanbul, Turkey
[wpgmappity id=”86″]

 

 

Gallery

Related Projects

MBE METRO PROJECT TOKİ STATION SHORING WORKS

MBE METRO PROJECT TOKİ STATION SHORING WORKS

Completed Projects Deep Excavations Deep Foundations...
FERRERO DÜZCE NUT CRACKING AND SELECTION FACILITY

FERRERO DÜZCE NUT CRACKING AND SELECTION FACILITY

Completed Projects Deep Foundations Soil Improvement...
CSS METRO PROJECT S21B SWITCH STRUCTURE

CSS METRO PROJECT S21B SWITCH STRUCTURE

Completed Projects Deep Excavations Turkey
1915 Canakkale Bridge European Approach Viaduct Ground Treatment And Pile Works

1915 Canakkale Bridge European Approach Viaduct Ground Treatment...

Completed Projects Deep Excavations Soil Improvement...