The contract was signed on March 28, 2020 with SSN (STE STFA SGTM NADOR S.A.) for the Diaphragm Wall and Barrette Pile works at the Nador Port Project, which is under construction in Morocco. The project consists of 18,000 m3 of Diaphragm Wall with depths changing from 19 to 38 m and 6,000 m3 of Barrette Pile with depths changing from 8 to 16 m.

Project Description

Nador Port Project

  • Engineering

Project Features

Client
STE STFA SGTM NADOR S.A.
Key Quantities
Barrette Pile18,000 m3
Diaphragm Wall6,000 m2
Project Duration
Start Date01.11.2020
Finish Date01.12.2021
Duration13 months

 

Location

Morocco
[wpgmappity id=”2″]

 

 

Related Projects

MBE METRO PROJECT TOKİ STATION SHORING WORKS

MBE METRO PROJECT TOKİ STATION SHORING WORKS

Completed Projects Deep Excavations Deep Foundations...
FERRERO DÜZCE NUT CRACKING AND SELECTION FACILITY

FERRERO DÜZCE NUT CRACKING AND SELECTION FACILITY

Completed Projects Deep Foundations Soil Improvement...
CSS METRO PROJECT S21B SWITCH STRUCTURE

CSS METRO PROJECT S21B SWITCH STRUCTURE

Completed Projects Deep Excavations Turkey
ICITY TOWERS PROJECT

ICITY TOWERS PROJECT

Completed Projects Deep Excavations Deep Foundations...