Esentai Park Project covers, soil improvement by using jet grout columns of foundations of the tower; anchor and rock bolt installation works and shotcreting wokrs for the execution of the excavation pit. ENKA was the employer of the project and it was completed in 2006.
Project Description
Esentai Park – Tower Building
- Engineering
Project Features
Client
ENKA İnşaat ve Sanayi A.Ş.
Key Quantities
Jet Grout | 14,000 m |
Pre-Stressed Anchor | 3,050 m |
Rock Bolt | 9,100 m |
Shotcrete | 600 m2 |
Project Duration
Start Date | 01.02.2006 |
Finish Date | 01.09.2006 |
Duration | 7 Months |
Location
Almaty, Kazakhstan