Rock stabilization works between axes W0+000.00 – W0+185.00 of Maad Hospitality Tower Project in Mecca were carried out by Kasktaş in 2018. The contract for the rock stabilization works between axes W0+185.00 – N0+340.00, which are the continuation of the project, was signed with Maad International Co. on June 30, 2020. The project includes 10,500 m of rock bolt.

Due to the Covid-19 epidemic, the construction was started in June and completed on October 1, 2020.

Project Description

Maad Hospitality Tower Project North Side

  • Engineering

Project Features

Client
Maad International Co.
Key Quantities
Rock Bolt 10,500m
Project Duration
Start Date 01.06.2020
Finish Date 01.10.2020
Duration 4 Mouths

 

Location

Arabia

 

 

Related Projects

MBE METRO PROJECT TOKİ STATION SHORING WORKS

MBE METRO PROJECT...

Completed Projects Deep...
FERRERO DÜZCE NUT CRACKING AND SELECTION FACILITY

FERRERO DÜZCE NUT...

Completed Projects Deep...
CSS METRO PROJECT S21B SWITCH STRUCTURE

CSS METRO PROJECT...

Completed Projects Deep...
ICITY TOWERS PROJECT

ICITY TOWERS PROJECT

Completed Projects Deep...