The contract was signed on March 28, 2020 with SSN (STE STFA SGTM NADOR S.A.) for the Diaphragm Wall and Barrette Pile works at the Nador Port Project, which is under construction in Morocco. The project consists of 18,000 m3 of Diaphragm Wall with depths changing from 19 to 38 m and 6,000 m3 of Barrette Pile with depths changing from 8 to 16 m.

Project Description

Nador Port Project

  • Engineering

Project Features

Client
STE STFA SGTM NADOR S.A.
Key Quantities
Barrette Pile 18,000 m3
Diaphragm Wall 6,000 m2
Project Duration
Start Date 01.11.2020
Finish Date 01.12.2021
Duration 13 months

 

Location

Morocco

 

 