The contract was signed on March 28, 2020 with SSN (STE STFA SGTM NADOR S.A.) for the Diaphragm Wall and Barrette Pile works at the Nador Port Project, which is under construction in Morocco. The project consists of 18,000 m3 of Diaphragm Wall with depths changing from 19 to 38 m and 6,000 m3 of Barrette Pile with depths changing from 8 to 16 m.
Project Description
Nador Port Project
- Engineering
Project Features
Client
STE STFA SGTM NADOR S.A.
Key Quantities
Barrette Pile | 18,000 m3 |
Diaphragm Wall | 6,000 m2 |
Project Duration
Start Date | 01.11.2020 |
Finish Date | 01.12.2021 |
Duration | 13 months |
Location
Morocco