Serdtse Stolitse Multifunctional Complex Building Phase-2

The contract for the Bored Pile, Pipe Pile and Anchor works within the scope of the Serdtse Stolitse Multifunctional Complex Building Project, located in Shelepihinskaya Street, Moscow, was signed with Ant Yapı on April 24, 2019. Within the scope of the project, there are 2,300 m of Bored Pile; 9,200 m of Anchor and 3,000 m of Pipe Pile works. Installations were started on April 1, 2019 and completed on September 1, 2019.

Project Description

Serdtse Stolitse Multifunctional Complex Building Phase-2

  • Engineering

Project Features

Client
Esta Construction
Key Quantities
Anchor 9,200 m
Bored Pile 2,300 m
Project Duration
Start Date 01.04.2019
Finish Date 01.09.2019
Duration 5 Mouth

Location

Moscow,  Russia

 

 

Gallery

Related Projects

Prince George Wharf Nassau Cruise Port Project

Prince George Wharf...

Completed Projects Deep...
Masar Project ST 06 Bored Pile Works

Masar Project ST...

Completed Projects Deep...
BMT Container Terminal

BMT Container Terminal

Basrah Completed Projects...
NADOR WEST MED PORT PROJECT

NADOR WEST MED PORT...

Completed Projects Deep...