Serdtse Stolitse Multifunctional Complex Building Phase 4

Following the completion of the Test Pile works of the Serdtse Stolitse Phase-4 Project, located in Shelepihinskaya, the contract was signed with Ant Yapı for the Bored Pile and Anchor works.

Within the scope of the project, there are 3,900 m of Bored Pile and 1,200 m of Anchor works. Anchor execution was completed on September 21, 2020. Bored pile installation was commenced on October 17, 2020. 90% of the bored pile work has been completed and all work is planned to be finished by the end of December 2020.

Project Description

Serdtse Stolitse Multifunctional Complex Building Phase 4

  • Engineering

Project Features

Client
Ant Yapı
Key Quantities
Bored Pile 3,900 m
Anchor 1,200 m
Project Duration
Start Date 21.09.2020
Finish Date Current
Duration

 

Location

Arabia

 

 

Related Projects

Masar Project ST 06 Bored Pile Works

Masar Project ST...

Completed Projects Deep...
BMT Container Terminal

BMT Container Terminal

Basrah Current Projects...
Nador Port Project

Nador Port Project

Current Projects Deep...
Masar Project Package A Shoring Works

Masar Project Package...

Asia Current Projects...