Shelepihinskaya Project

The contract for the Multifunctional Residence and Facility Complex, located in Moscow, has been signed with ANT YAPI. Within the scope of the project; 8,500 m of Bored Pile with Ø 100-150 cm diameters has been completed.

Project Description

Shelepihinskaya Project

  • Engineering

Project Features

Client
ANT YAPI
Key Quantities
Bored Pile 8,500 m
Project Duration
Start Date 15.10.2017
Finish Date 21.04.2018
Duration 7 Months

Location

Moscow, Russia

 

 