In this project, where the employer is Sedef Gemi İnşaat, a total of 168,000 m Jet Grout Column and 35,000 m Bored Pile were installed in Tuzla Sedef Shipyard between 2005-2008.
Project Description
Tuzla Sedef Shipyard
- Engineering
Project Features
Client
Sedef Gemi İnşaat
Key Quantities
Bored Pile | 35,000 m |
Jet Grout Column | 168,000 m |
Project Duration
Start Date | 01.04.2005 |
Finish Date | 01.12.2008 |
Duration | 45 Months |
Location
Istanbul, Turkey