In Tsvetnoy Project, a local subcontractor was started geotechnical works. However, due to the excessive unpredictable displacements encountered, KASKTAŞ was involved in the Project. Within the content of the remedial measures, a total of 550 m steel pipe pile, 1,140 m secant bored pile and 2,400 m top down bored piles were successfully executed in order to strengthen the existing shoring system.

Project Description

Tsvetnoy Multifunctional Complex Project

  • Engineering

Project Features

Client
ENKA Capital Group
Key Quantities
Steel Pipe Pile550 m
Secant Pile1,140 m
Top Down2,400 m
Project Duration
Start Date01.06.2007
Finish Date01.10.2007
Duration4 Months

Location

Moscow, Russian Federation
[wpgmappity id=»69″]

 

 

Gallery

Related Projects

ICITY TOWERS PROJECT

ICITY TOWERS PROJECT

Completed Projects Deep Excavations Deep Foundations...
ПРОЕКТ ЖИЛОЙ КОМПЛЕКС СИМВОЛ

ПРОЕКТ ЖИЛОЙ КОМПЛЕКС СИМВОЛ

Asia Completed Projects Deep Foundations Russian Federation
КУТУЗОВСКИЙ КОМПЛЕКС СТРОИТЕЛЬСТВА ЭТАП 1 И 2

КУТУЗОВСКИЙ КОМПЛЕКС СТРОИТЕЛЬСТВА...

Asia Completed Projects Deep Excavations Deep Foundations...
КОМПЛЕКС СЕРДЦЕ СТОЛИЦЫ, ЭТАП 4, ПРОЕКТ

КОМПЛЕКС СЕРДЦЕ СТОЛИЦЫ, ЭТАП 4, ПРОЕКТ

Asia Completed Projects Deep Excavations Deep Foundations...