Within the scope of the contract, which consists of the Domodedovo Airport Reconstruction Project in Moscow, signed with ANT YAPI San. ve Tic. A.Ş.; 8,000 m of Bored Pile has been completed as Stage 1 and 2. All installations will be completed when the additional 500 m of Bored Pile is executed.

Project Description

Domodedovo Airport Project

  • Engineering

Project Features

Client
ANT YAPI
Key Quantities

Diaphragm Wall500 m
Pile8,500 m

Project Duration

Start Date02.02.2017
Finish Date01.12.2018
Duration22 Months

Location

Moscow, Russia
[wpgmappity id=”2″]

 

 

Gallery

Related Projects

مشروع فيريرو دوزجي لتكسير واختيار البندق

مشروع فيريرو دوزجي لتكسير واختيار...

Completed Projects Deep Foundations Soil Improvement...
مشروع مترو CSS مبنى S21B

مشروع مترو CSS مبنى S21B

Completed Projects Deep Excavations Turkey
ICITY TOWERS PROJECT

ICITY TOWERS PROJECT

Completed Projects Deep Excavations Deep Foundations...
مشروع ميناء الأمير جورج وارف ناسو

مشروع ميناء الأمير جورج وارف ناسو

Completed Projects Deep Excavations Deep Foundations...