anemptytextlline
-
مشروع تأهيل ميناء أكتاوAktau is Kazakhstan's main port on the Caspian Sea and serves as the major logistics base for the offshore oil fields. The ENKA-Bechtel joint venture signed the contract with Kazakhstan's Ministry of Transportation for the Aktau Port rehabiliation project. The...
-
Jeddah Hilton Hotel
anemptytextlline
Located on the Corniche Road in Jeddah, this project consists of a hotel building, function hall and apartment blocks constructed between 1995 and 2001. A total of 36,000 m of 100 cm diameter skin and base grouted bored piles were... -
Mostar Bridge
anemptytextlline
The historical Mostar Bridge collapsed on November 9, 1993 as a result of bombing during the civil war in the former state of Yugoslavia. Reconstruction of the bridge and the historical environment were performed under the supervision of the World... -
Poti Port Petroleum Products Storage and Handling Terminal Project
anemptytextlline
The Poti Sea Port is a major seaport and harbor of the eastern Black Sea coast at the mouth of the Rioni River in Poti, Georgia. 11,000 m Stone Column installation completed successfully by Kasktaş as a subcontractor of Üstay... -
Artvin Deriner Dam
anemptytextlline
The 670 MW Deriner Dam, located on the Çoruh River in the Eastern Black Sea Region, is the largest dam in Turkey and the fifth largest concrete dam in the world with a height of 247 m. Construction of dam... -
C&WP Topside Project
anemptytextlline
This project consists of the modernization and strengthening of quayside works; where petroleum platforms will be constructed. Ground improvement by stone column method was implemented under the unloading berth area; where extremely high loads were placed. In addition to 10,000... -
Tengiz & Munay Daria Projects
anemptytextlline
A total of 17,000 m reinforced concrete precast driven pile and 27,500 m2 sheet piles were driven by executed by KASKTAŞ. Project DescriptionTengiz & Munay Daria Projects Engineering Project Features Client Munay Daria Key Quantities R.C. Driven Pile 17,000 m Sheet Pile 27,500 m2 Tie Rods Installation 94 no. Project Duration Start... -
Oued Athmania Dam Project
anemptytextlline
Within the scope of the Oued Athmania Dam Project in Mila, 11,000 m of 650 mm diameter jet grout columns were performed, within the dam construction works, a total of 35,050 m of drilling for grouting and drainage, 5,300 m... -
Four Seasons Bosphorus Hotel
anemptytextlline
For the excavation of foundation excavation pit for the Four Seasons Bosphorus Hotel, located very close to Istanbul Bosphorus, an anchored piled wall shoring system was implemented with a depth of 18 m. In order to provide impermeability of shoring... -
Aramco Rabigh Development Project
anemptytextlline
In the content of Aramco Rabigh Development Project, a total of 22,000 m bore pile and 51,000 m stone column installation works were successfully completed. Project DescriptionARAMCO Rabigh Development Project Engineering Project Features Client Consolidated Contractors Company Key Quantities Bored Pile 22,000 m Stone Column 51,000 m Project Duration Start Date 01.06.2006 Finish... -
Esentai Park - Tower Building
anemptytextlline
Esentai Park Project covers, soil improvement by using jet grout columns of foundations of the tower; anchor and rock bolt installation works and shotcreting wokrs for the execution of the excavation pit. ENKA was the employer of the project and... -
White Square Office Center Project
anemptytextlline
The White Square Office Center, whose client was the AIG Lincoln-Coalco Partnership, consists of 3 office buildings near the Belaruskaya Subway Station and covers a total construction area of 109,000 m2. A total of 4,700 m of bored pile installation... -
Mirax Plaza
anemptytextlline
A total of 11,000 m of bored piles; varying from 1,000-1,200 mm diameter were installed at the Mirax Plaza Project. This project consists of the construction of two high-rise buildings, 41 and 47 stories tall. The piling works began at... -
Shakhtar Donetsk Stadium
anemptytextlline
The new Stadium, located in Leninsky Komsomol Park, Donetsk, home of FC Shakhtar and is the first stadium in Ukraine to aspire to UEFA and FIFA 5-star status with seating capacity for 50,000 spectators. The project has seen the driving... -
Jeddah King Abdul Aziz International Airport
anemptytextlline
The project, located within King Abdul Aziz Airport area, includes the expansion of existing domestic and international passenger terminals. Bored pile installation works were completed in two different sites, the north and south terminals. Project DescriptionJeddah King Abdul Aziz International Airport... -
Medina Central Area Development Project
anemptytextlline
Since the middle of the 1980s the Prophet’s Mosque (Masjid Al Haram Al Sharif, Masjid An-Nabawi) in Medina has been expanded with the area around the mosque developed by The Medina Central Area Development Project. In accordance with this ongoing... -
Tsvetnoy Multifunctional Complex
anemptytextlline
In Tsvetnoy Project, a local subcontractor was started geotechnical works. However, due to the excessive unpredictable displacements encountered, KASKTAŞ was involved in the Project. Within the content of the remedial measures, a total of 550 m steel pipe pile, 1,140... -
On-Shore Processing Facility, Sakhalin Island
anemptytextlline
On the northeastern coast of Sakhalin Island in the Russian Federation, a total of 100,000 m of 500-600 mm diameter bored pile and 2,000 m2 of sheet pile wall were executed in three phases at the On-shore Processing Facility Project... -
Tuzla Sedef Shipyard
anemptytextlline
In this project, where the employer is Sedef Gemi İnşaat, a total of 168,000 m Jet Grout Column and 35,000 m Bored Pile were installed in Tuzla Sedef Shipyard between 2005-2008. Project DescriptionTuzla Sedef Shipyard Engineering Project Features Client Sedef Gemi İnşaat Key Quantities Bored Pile 35,000... -
Paveletskaya Underground Complex
anemptytextlline
Paveletskaya Square Project is an underground trade center to be built on the Paveletskaya square of Moscow city center. Our company has undertaken the construction of diaphragm wall, bored pile and ground improvement works within the content of the Project.... -
Albanian Motorway Project
anemptytextlline
Albanian Motorway Project was undertaken by Enka and Bechtel in September, 2006. The Rreshen-Kalimash Motorway Project is a key connection between Durres Port, Albania’s primary harbor on the Adriatic Sea, and Kosovo. The Rreshen-Kalimash motorway’s main purpose is to serve... -
Algeria Motorway Project
anemptytextlline
This motorway is a major national project being undertaken by the Algerian government. Traversing the country, the motorway will stretch from the Tunisian border in the east to the Moroccan border in the west, for a total distance of 1,200... -
Tula Cement Factory
anemptytextlline
The Tula Cement Plant belonging to Heidelberg Cement was located in Tula, Russia. Under the main contactor Betatek, KASKTAŞ successfully completed a total of 37,000 m of bored piles with various diameter and length. Before execution of piles, a number... -
Vyborg Compressor Station
anemptytextlline
In the content of Nord Stream Project of Gazprom 6,500 m bored piles constructed. The city of Vyborg was built on a volcanic structure, which makes the project important. Massive granite and granodiorite type rocks were observed throughout the region.... -
White Garden Project
anemptytextlline
The White Garden Project, whose client is Ant Yapı, consists of 2 number of office buildings and it was planned as the continuation of the White Square Project. Within the scope of the project, 272 Top Down pile were successfully... -
Al Jawhara Tower Project
anemptytextlline
The 40-storey Al Jawhara Tower; which is located on the Corniche Road in Jeddah; consists of luxurious penthouses and apartments. A total of 3,600 m, 60 cm and 80 cm diameter secant piles; 10,750 m 90 cm and 120 cm... -
Borusan Gemlİk Projects
anemptytextlline
A total of 21,860 m of bored piles and 17,780 m of DSM Columns were installed at the Bursa Gemlik ERW Pipe Plant of Borusan Mannesmann. Also within the scope of Gemlik Port Facilities Renovation and Consolidation Project 34,000 m... -
Levent Zorlu Project
anemptytextlline
Four (4) different shoring systems of Zorlu Levent Project with 20 m to 27 m excavation depth were designed by KASKTAŞ. In order to perform the excavation in dry condition and safely without causing any hazard to surrounding structures and... -
Lamar Towers
anemptytextlline
The Lamar Towers in Jeddah; which is 50 m away from the Red Sea; consist of two multi functional towers and will be one of the tallest buildings in Jeddah at a 335 m height. The podium structure consists of... -
Multi-Purpose Public Buildings in Smolenskaya
anemptytextlline
Diaphragm wall with a thickness of 600 mm and 1,000 mm diameter top-down bored pile construction works were successfully completed within the scope of the Smolenskaya Multi-Purpose Public Building Project; which consists of a 12-storey shopping center and office buildings.... -
İzmit Tüpraş Refinery Upgrading Projects
anemptytextlline
Within the scope of Izmit Tüpraş Refinery Upgrading Projects, soil improvement works were completed under 5 different Employers. Between 2011 and 2012, a total of 162,000 m Jet Grout, 21,500 m Foundation Piles and 3,800 m Barette Piles were installed... -
Kashagan Oil Field Development
anemptytextlline
The Kashagan field is located in the Kazakhstan sector of the Caspian Sea and extends over a surface area of approximately 75 kilometers by 45 kilometers. The reservoir lies some 4,200 meters below the shallow waters of the northern part of the... -
Metro Bank Project
anemptytextlline
A total of 18,285 m2 Diaphragm Wall, 3,150 m Grout Drilling and 90 m3 Grouting works were completed within the content of the Metrobank, one of the biggest banks of the Russian Federation, Project. Project DescriptionMetro Bank Project Engineering Project Features Client Alto-Assets Key Quantities Diaphragm... -
Ford Otosan Automobile Plant
anemptytextlline
Within the scope of Ford Otosan Automobile Factory in Gölcük, bored piles, jet grout columns and stone columns were successfully executed under the foundations of the different strcutures. 13 months after the project started; in other words when 90% of... -
Jeddah Storm Water Drainage Project
anemptytextlline
This project was designed in order to control and divert storm water towards to the sea. The whole project consists of 8 Packages with 5 Dams and 3 Channels/Drainage and outfalls. The New Drainage system runs at a stretch of... -
Kuntsevo Multifunctional Trade & Business Center
anemptytextlline
Kuntsevo Multifunctional Trade & Business Center was built in Moscow with an area of 26,800 m2. The 25 m deep excavation pit was performed by a deep shoring system consisting of 45 m deep and D=80 cm diaphragm wall supported... -
Metropol Ataşehir Project
anemptytextlline
2,650 m Barette piles were constructed within the content of the Metropol Istanbul Project, one of the highest buildings in Europe with a 250-meter skyscraper. Project DescriptionMetropol Ataşehir Project Engineering Project Features Client Varyap GAP Key Quantities Barette Pile 2,650 m Project Duration Start Date 01.06.2013 Finish Date 01.10.2013 Duration 4 Months LocationIstanbul, Turkey Gallery... -
4×125 Najybia Gas Turbine Power Plant
anemptytextlline
Najybia Power Plant Project was successfully completed by ENKA. The project, located near Basrah, is part of a master plan developed and implemented by Republic of Iraq’s Ministry of Electricity to increase the power generation capacity to meet the rapid... -
İzmit Bay Suspension Bridge Project
anemptytextlline
Osman Gazi Bridge Projects Within the scope of the Osman Gazi Bridge Project; 4 different works; such as diaphragm wall works at South Anchorage Block and South Approach Viaducts, sheet pile driving and extracting works at Dry Dock, soil improvement by... -
Western High Speed Diameter Motorway Project
anemptytextlline
St. Petersburg Western High-Speed Diameter Motorway Project is one of the most important public-private partnership (PPP) agreement realized in Russia up to now. Within the scope of the Project a series of bridges combining the islands and a 47 km long... -
NEF Projects
anemptytextlline
NEF 163 and NEF 11 Multi Functional Residence and Office Projects were completed in 2011. Within the scope of NEF 163 4,400 m Anchors and 350 m Soil Nails were completed. Within the content of NEF 11 Project 5,500 m... -
Eroğlu Skyland Project
anemptytextlline
Skyland Project consists of 3 number of tower (Offices, Residences and Hotel) and a shopping with wellness center. This is the deepest excavation project with its 76 m depth supported with anchors not only in Europe but also in the... -
Moscow International Business Center
anemptytextlline
Moscow City, or the Moscow International Business Center by its full name, is situated four kilometers west of the Kremlin on Krasnopresnenskaya (an embankment of the Moscow River), and is one of the largest and most ambitious construction projects. The... -
New Ashgabat International Airport
anemptytextlline
The new Ashgabat International airport was built to replace existing airport facilities in order to respond to the rapidly growing domestic and international passenger traffic in Turkmenistan. Within the scope of the project, its main contractor was Polimeks, 120,000 m... -
Eurasia Tunnel - Istanbul Strait Road Tube Crossing Project
anemptytextlline
Within the scope of Eurasia Tunnel Project (Istanbul Strait Road Tube Crossing Project) that connects Asian and European continents with highway tunnel under seabed for the first time; excavation support systems of temporary structures called as transition boxes and prepared... -
Mecca Holy Haram Development Project
anemptytextlline
The increasing number of pilgrims, Mecca receives, has necessitated expansion of the Holy Mosque (Al Masjid Al Haram), as well as development projects located in the holy sites and several high-rise tower projects to accommodate the greater influx. Since its first... -
İzmir Aliağa Star Refinery Projects
anemptytextlline
İzmir Aliağa Star Refinery Projects Within the scope of İzmir Aliağa Refinery Project; which is the largest private sector investment project in Turkey, several sub-contract works have been carried out under different main contractors. Under these subcontracts; Terrace 5&6 Permanent SBMA Anchor... -
Alarko Kabataş Construction Site, Shoring Works of NATM, TBM and...
anemptytextlline
Within the scope of Kabataş-Mecidiyeköy-Mahmutbey Subway Project, shoring works of NATM, TBM and Turnout shaft in Kabataş, Istanbul has been carried out. The excavation depth of these three shafts vary between 43.10 m to 45.4 m and they are very... -
Jabal Al Ka’aba Project Phase 2
anemptytextlline
Within the scope of Mecca Development Project Phase-1 of Jabal Al Ka'aba Project was completed between 2003 and 2004. Besides slope stability project of the rock stabilization works in Phase 2 of the Jabal Al Ka'aba Project was also designed... -
Riyadh Metro Project Piling and Shoring Works
anemptytextlline
Riyad Metro - Line Number 3 Within the content of the Riyad Metro Project, one of the largest construction projects in Saudi Arabia, bored piles with 120 cm and 150 cm diameter in the Western Stretch region viaducts were completed. The... -
Mahall Bomonti İzmir Project
anemptytextlline
The Mahall Bomonti İzmir Project under construction is located at Bayraklı region in İzmir. The deep foundation system and shoring design of Mahall Bomonti İzmir Project; which has a maximum 20 m of excavation depth and partially under ground water... -
Ferko Line Office and Hotel Project
anemptytextlline
The shoring design of Ferko Line Project; which has 9 m of excavation depth and partially underground water level was accomplished by KASKTAŞ. In order to perform the excavation in dry condition and safely without causing any hazard to surrounding... -
Bahçeşehir University Education Building Project
anemptytextlline
A total of 7000 m2 diaphragm wall and 700 m2 baretta pile was constructed within the scope of Bahçeşehir University Education Building Project, which was started in October 2017. The project site in Besiktas is next the shoring line of... -
Michurinsky Bored Pile Project
anemptytextlline
Within the scope of the Michurinsky residency project in Moscow, 17,400 m of Bored Pile work has been completed. The completed piles have the following properties: After the concrete has been poured into each pile, a precast concrete pile is driven into... -
Mandarin Oriental Bosphorus Hotel Project
anemptytextlline
Mandarin Oriental Bosphorus Project Shoring and Foundation Works is an ESTA Gayrimenkul investment and the contract has been signed with Yapı Merkezi. Within the scope of the project; there are 21,600 m2 of Diaphragm Wall; 6,000 m of Pre-stressed Anchor;... -
Shelepihinskaya Project
anemptytextlline
The contract for the Multifunctional Residence and Facility Complex, located in Moscow, has been signed with ANT YAPI. Within the scope of the project; 8,500 m of Bored Pile with Ø 100-150 cm diameters has been completed. Project DescriptionShelepihinskaya Project Engineering Project... -
Multi-storey Car Park Project
anemptytextlline
The contract for the Multi-storey Car Park Project, which is located in MIBC Moscow-City Ring 3 Transportation Road, has been signed with ENKA CONSTRUCTION. Within the scope of the project; 3,500 m of Bored Pile with Ø 62 cm diameter... -
Krasnopresnenskaya Project
anemptytextlline
Within the scope of the contract signed with OOO BOES CONSTRUCTION for the Multifunctional Complex Project Bored Pile Works; 16,500 m of Bored Pile with Ø 88-100 cm diameters has been completed. The project is located in the Krasnopresnenskaya Region... -
Filicity Project
anemptytextlline
The contract of Multifunctional Residence Project Bored Pile Works, signed with ESTA CONSTRUCTION; 11,000 m of Bored Pile with Ø 120 cm diameter has been completed. The project, whose construction is still ongoing, is located in Bagrationovskaya Region, Moscow. Project... -
King Abdulaziz Roadway Project
anemptytextlline
King Abdulaziz Roadway Project, whose construction is ongoing in the Mecca, Saudi Arabia, consists of the construction of a new bridge that is connected to the Jeddah-Mecca Motorway. Within the scope of the project; 300 m of Bored Pile with... -
Çanakkale 1915 Bridge Project / European Anchor Block Excavation
anemptytextlline
The contract of the Çanakkale 1915 Bridge European Anchor Block Excavation Works has been signed with DLSY JV. Within the scope of the project which consists of Kınalı-Tekirdağ-Çanakkale-Savaştepe Highway; there are 5,400 m of Secant Pile; 9,500 m of Rock... -
مشروع مجمع توليد الطاقة الكهربائية بالعراق بذي قار والسماوة
anemptytextlline
تم توقيع عقد مشروع محطة توليد الكهرباء ذات الدورة المركبة بسعة ٧٥٠ ميغاواط مع شركة إنكا للإنشاءات في العراق في منطقتي ذي قار والسماوة، والذي يتشرط صنعها خوازيق محفورة عميقة. ومن ضمن نطاق المشروع، تم الانتهاء من ١٨,٠٠٠ متر طولي... -
Maad Hospitality Tower Project
anemptytextlline
The contract for the Maad Hospitality Tower Project, which will be built in Mecca, Saudi Arabia, has been signed in April 2018. The project consists of the rock bolt and shotcrete works which are executed on the existing slope surface.... -
Dimitrovsky Project
anemptytextlline
The contract of the MR Group Multifunctional Complex Project Bored Pile Works has been signed with ANTTEQ. The project is ongoing in Dimitrovskiy Region in Moscow. Within the scope of the project, there are 13,000 m of Bored Pile work.... -
Domodedovo Airport Project
anemptytextlline
Within the scope of the contract, which consists of the Domodedovo Airport Reconstruction Project in Moscow, signed with ANT YAPI San. ve Tic. A.Ş.; 8,000 m of Bored Pile has been completed as Stage 1 and 2. All installations will... -
Çanakkale 1915 Bridge Project / Asian Anchor Block Excavation
anemptytextlline
The contract for the Çanakkale 1915 Bridge Asian Anchor Block Excavation Works, which is in the scope of the Kınalı-Tekirdağ-Çanakkale-Savaştepe Highway Project, has been signed with DLSY JV in August 8th, 2018. Within the scope of the project; there are... -
Üsküdar Underground Car Park
anemptytextlline
Within the scope of the contract, which consists of the Hakimiyeti Milliye Bazaar and Underground Car Park Project located in Üsküdar, signed with PLT İnş. San. ve Tic. A.Ş.; there are 15,600 m2 of Diaphragm Wall and 7,000 m of... -
Action Development Project
anemptytextlline
Within the scope of the contract signed with ANT YAPI for the Office and Hotel Project Diaphragm Wall and Top-Down Bored Pile Works; 6,000 m2 of Diaphragm Wall and 2,000 m of Bored Pile works have been completed. The project,... -
1915 Canakkale Bridge European Approach Viaduct Ground Treatment And Pile...
anemptytextlline
Following the successful completion of European and Asian Anchor Block excavation support works, the contract for the construction of 365 m long European Approach Viaduct ground treatment and piling works has been signed with the consortium DLSY (Yapı Merkezi-Daelim-SK-Limak). Within the... -
Sadoviy Kvartal Deep Excavation Support Project
anemptytextlline
Within the scope of Stage 3 and 5 construction works of Sadoviy Kvartal Multifunctional Residence with Underground Car Park Project located in Hamovniki Region, which is one of the most prestigious district of Moscow, there are diaphragm wall and jet... -
Saharova Red 7 Project Foundation Pile Works
anemptytextlline
The contract of the MR Group Multifunctional Complex Project Bored Pile Works has been signed with ANTTEQ. The project is ongoing in Dimitrovskiy Region in Moscow. Within the scope of the project, there are 13,000 m of Bored Pile work.... -
يو اس تي المسك لأعمال تحسين التربة واللباب والورق
anemptytextlline
بدأت في عام 1973 مجموعة إلم جروب في إنشاء مجمع صناعة الغابات في منطقة سيبيريا، بمدينة يو اس تي المسك (اوركتسكي اوبلاست) بقرار من مجلس وزراء الاتحاد السوفيتي. توفر إلم جروب 75% من متطلبات السليلوز السنوية للاتحاد السوفيتي وهي مصنفة... -
مشروع أنابيب مياه طريق الملك عبد العزيز ونهاية امتداد 9
anemptytextlline
تم توقيع عقد أعمال مسامير التربة والخرسانة المرشوشة التي تمنع التشوه الذي يحدث أثناء حفر خط المياه النظيفة 700 مم والذي يغذي الحرم ضمن نطاق مشروع طريق الملك عبد العزيز مع شركة نسما وشركاهم للمقاولات المحدودة في 9 يوليو 2019.... -
مشروع مخرج الرياض 10
anemptytextlline
تقوم الشركة السعودية للمشاريع الترفيهية، قام بتأسيسها الصندوق العام السعودي عام 2017، ببناء مجالات النشاط الاجتماعي في جميع أنحاء الدولة. تم توقيع عقد إنشاءات مسامير التربة والخرسانة المرشوشة ضمن نطاق مشروع مخرج الرياض 10 سلسلة المشاريع الترفيهية، وهو أحد مشاريع... -
مشروع طريق الملك عبد العزيز نهاية امتداد 4
anemptytextlline
تم توقيع عقد إنهاء أعمال التدعيم لامتداد 4 ضمن نطاق مشروع طريق الملك عبد العزيز مع شركة نسما وشركاه للمقاولات في 21 مايو 2019. ولقرب المشروع من الحرم وموقع خط تدفق مياه زمزم بداخله في موقع المشروع، تم طلب عدم... -
مشروع إنشاء محطات تحلية المياه بالأقمار الصناعية، محطة حقل
anemptytextlline
ضمن نطاق مشروع إنشاء محطات تحلية المياه بالأقمار الصناعية، تهدف وزارة البيئة في المملكة العربية السعودية إلى بناء 8 محطات لتحلية المياه على شاطئ البحر الأحمر. تم توقيع عقد إنشاء الخوازيق القاطعة في نطاق محطة حقل مع شركة بيكس للإنشاءات... -
مشروع مدينة الملك عبدالله الاقتصادية لتحلية المياه بالطاقة الشمسية
anemptytextlline
توفير المياه لمدينة الملك عبد الله الاقتصادية؛ والتي تقع على ساحل البحر الأحمر، والتي سيتم دعمها بمحطة تحلية المياه بالطاقة الشمسية بقدرة تحلية 30.000 متر مكعب من مياه البحر للاستخدام المحلي في المدينة. تم توقيع عقد أعمال الخوازيق القاطعة لهيكل... -
مشروع إنشاء محطات تحلية المياه بالأقمار الصناعية، محطة أملج
anemptytextlline
تهدف وزارة البيئة في المملكة العربية السعودية ضمن نطاق مشروع إنشاء محطات تحلية الأقمار الصناعية، إلى بناء 8 محطات لتحلية المياه على شاطئ البحر الأحمر. ومحطة أملج هي واحدة من هذه المحطات الثمانية ولديها القدرة على تحلية 18000 متر مكعب... -
مشروع فندق بلغاري
anemptytextlline
تم توقيع عقد أعمال الخوازيق القاطعة والركائز من أعلى إلى أسفل ضمن نطاق مشروع فندق بلغاري، الكائن في موسكو مع شركة أنتيك في 11 أكتوبر 2019. يشمل المشروع 7500 من الخوازيق القاطعة و 2400 متر من أعلى إلى أسفل. بدأ... -
مبنى مجمع سيرتدتسر ستوليتس متعدد الوظائف المرحلة – 2
anemptytextlline
تم توقيع عقد حفر الخوازيق وأنبوب الخوازيق والركيزة ضمن نطاق مشروع مبنى مجمع سيرتدتسر ستوليتس متعدد الوظائف، الكائن في شارع شيلفسكاويا، موسكو، مع آنت يابي في 24 أبريل 2019. ويوجد ضمن نطاق المشروع 2300 متر من حفر الخوازيق؛ و 9200... -
مشروع هافسكايا للاسكان
anemptytextlline
تم توقيع عقد أعمال الجدار الحاجز ضمن نطاق مشروع هافسكايا للإسكان، الكائن في موسكو، مع بوترانز في 24 أبريل 2019. تم إنجاز الجدار الحاجز بمساحة 3000 متر مربع بين 27 مايو و 21 يونيو 2019. العميل: بوترانز Proje TanımıHavskaya Housing Project Mühendislik Proje... -
مشروع مجمع ألسوفيسكي متعدد الوظائف
anemptytextlline
مشروع مجمع ألسوفيسكي متعدد الوظائف تم توقيع عقد أعمال حفر الخوازيق ضمن نطاق مشروع مجمع ألسوفيسكي متعدد الوظائف الكائن في موسكو، مع أنتيك بتاريخ 25 مارس 2019. بدأ تنفيذ حفر الخوازيق بطول 1600 متر في 10 أبريل 2019 وانتهى في 12... -
مشروع مولكومنلي للاسكان المرحلة - 2
anemptytextlline
يقع عقد أعمال حفر الخوازيق ضمن نطاق مشروع مولكومنلي للإسكان - المرحلة 2، في موسكو وهو استثمار لمجموعة كابيتال جروب، والذي تم توقيعه مع أنتيك في 8 أبريل 2019. يتضمن المشروع 7000 متر من أعمال حفر الخوازيق. بدأت أعمال التثبيت... -
مشروع سكاكا الكهروضوئي المستقل 405 ميجاوات
anemptytextlline
حيث أنه أول مشروع للطاقة المتجددة في إطار البرنامج الوطني للطاقة المتجددة، يقع مشروع سكاكا 405 ميجاوات على بعد 30 كم خارج مدينة سكاكا في منطقة الجوف ويغطي مساحة 6 كيلومتر مربع. وعند انجازه سوف يزود المشروع 45000 أسرة بالكهرباء... -
أعمال تثبيت المنحدر في جبل الكعبة - المرحلة 3
anemptytextlline
تم توقيع العقد مع شركة عبد اللطيف جميل للاستثمار العقاري لمشروع جبل الكعبة المرحلة الكائن في مكة المكرمة. يوجد ضمن نطاق المشروع من مسامير الصخور و أعمال الخرسانة المرشوشة. Project DescriptionImprovement of Tahliah Madinah Intersection Underpass Engineering Project Features Client Abdul Latif Jameel Real... -
مبنى مجمع سيردتس ستويلتس متعدد الوظائف المرحلة – 4
anemptytextlline
بعد إنجاز أعمال اختبار الخوازيق لمشروع سيردتس ستويلتس المرحلة – 4، الكائن في شيلفنسكايا، م توقيع عقد مع آنت يابي لأعمال حفر الخوازيق والركائز. يشمل نطاق المشروع 3900 م من الخوازيق و 1200 م من أعمال الركائز. تم الانتهاء من تنفيذ... -
مشروع مجمع كوتوفسكي - المراحل 1 و 2
anemptytextlline
تم توقيع عقد أعمال الخوازيق ضمن نطاق مشروع مجمع كوتوفسكي الكائن في مدينة موسكو، مع آنتيك في 28 يوليو 2020. يشمل المشروع 3800 متر من الخوازيق. يتم تنفيذ الخوازيق على منصة من الحديد. بدأت عمليات التنفيذ في 31 يوليو 2020. ومن... -
مشروع مجمع سيمفول
anemptytextlline
تم توقيع العقد في 14 أغسطس 2020 مع آنت يابي لأعمال أنابيب الخوازيق في نطاق مشروع مجمع سيمفول، وهو استثمار دونستروف في موسكو. تم الانتهاء من 5,300 م من أعمال أنابيب الخوازيق ضمن نطاق المشروع. العميل: آنت يابي Project Descriptionsimvol-complex-project Engineering Project Features Client Ant... -
أعمال تدعيم برج إن سي إم إس
anemptytextlline
تم توقيع العقد في 19 سبتمبر 2020 مع مفاهيم الإعمار لأعمال تدعيم مبنى البرج ضمن نطاق مبنى الشركة الوطنية لمشروع النظام الميكانيكي، الكائن في الرياض. يتكون العقد من أعمال الخوازيق القاطعة وأعمال الركائز. بالنسبة للمشروع الذي بدأ في أكتوبر 2020؛ تم... -
مشروع مسار
anemptytextlline
مشروع مسار، هو مشروع ضخم يجري إنشاؤه حاليا في مدينة مكة المكرمة بالمملكة العربية السعودية، يهدف المشروع إلى تمكين وصول زوار الحرم المكي بنظام مترو الأنفاق عبر قطار الحرمين الذي يربط المدينة المنورة و جدة و مكة المكرمة. تم توقيع... -
مشروع ميناء الناظور
anemptytextlline
تم توقيع العقد في 28 مارس 2020 مع إس إس إن SSN (STE STFA SGTM NADOR S.A.) لأعمال الجدار الحاجز والخوازيق في مشروع ميناء الناظور قيد الإنشاء في المغرب. يتكون المشروع من 13.900 متر مربع من الجدار الحاجز و 6000... -
محطة حاوية بي إم تي
anemptytextlline
تم توقيع العقد مع شركة إنكا كونستركشن لمتيد فرع العراق في 27 مايو 2020 لإنشاء الخوازيق ضمن نطاق ساحة محطة الحاويات متعددة الأغراض في ميناء أم قصر البصرة الواقعة في العراق. بدأ بناء الخوازيق في 27 سبتمبر 2020 ومن المقرر الانتهاء... -
شروع مسار المحطة - 6 لأعمال الخوازيق
anemptytextlline
م توقيع العقد مع شركة نسما وشركاهم للمقاولات المحدودة لتنفيذ الخوازيق الصخرية تحت أساس الجسر الذي سيتم بناؤه على الطريق الدائري الأول الكائن في منطقة المحطة – 6 ضمن نطاق مشروع مسار. تم الانتهاء من 850 م من الركائز داخل نطاق... -
مشروع ميناء الأمير جورج وارف ناسو
anemptytextlline
اقترحت حكومة جزر البهاما استراتيجيات لتكبير الرحلات السياحة البحرية من خلال تطوير الميناء الحالي في ميناء الرحلات البحرية الأمير جورج وارف ناسو. وسيؤدي تجديد وتوسعة الميناء إلى زيادة السعة والسماح للركاب بتجربة أفضل. وقع شركة كاسكتاش عقدًا مع شركة إنكا للإنشاءات... -
ICITY TOWERS PROJECT
anemptytextlline
ICITY Towers Project is a complex building project consisting of two skyscrapers in the Moscow City region. The contract was signed with MR Group for Piling, Soil Improvement and Excavation Works within the scope of the shoring works of the... -
مشروع مترو CSS مبنى S21B
anemptytextlline
اكتسب بناء خط مترو "شيكميكوي - سانجاك تيبي - سلطان بيلي" الذي تم بناؤه كامتداد لمشروع مترو أوسكودار - عمرانية - شكمكوي زخمًا في عام ٢٠٢١. تم توقيع عقد مع شراكة عادية بين دوغوش – يابي مركزي - أوزالتين لأعمال... -
مشروع فيريرو دوزجي لتكسير واختيار البندق
anemptytextlline
تم توقيع العقد مع شركة "تابي إنشاءات" لأعمال تحسين التربة في نطاق مشروع فيريرو دوزجي لتكسير واختيار البندق. ضمن نطاق المشروع، تم الانتهاء من تنفيذ الأعمدة الحجرية ودك التربة (DSM) والخوازيق المحفورة. بالإضافة إلى تنفيذ مجموعة متنوعة من التطبيقات الجيوتقنية،...