A total of 18,285 m2 Diaphragm Wall, 3,150 m Grout Drilling and 90 m3 Grouting works were completed within the content of the Metrobank, one of the biggest banks of the Russian Federation, Project.
Project Description
Metro Bank Project
- Engineering
 
Project Features
Client
					Alto-Assets
				
			Key Quantities
| Diaphragm Wall | 18,285 m2 | 
| Cementation Drilling | 3,150 m | 
| Cementation | 90 m3 | 
Project Duration
| Start Date | 01.06.2011 | 
| Finish Date | 01.09.2012 | 
| Duration | 15 Months | 
Location
Moscow, Russian Federation