The new Ashgabat International airport was built to replace existing airport facilities in order to respond to the rapidly growing domestic and international passenger traffic in Turkmenistan. Within the scope of the project, its main contractor was Polimeks, 120,000 m Dia.: 800 mm stone column and 150,000 m 600 mm çapında jet grout column installation works carried out by KASKTAŞ. The new airport was opened in 2016.
Project Description
New Ashgabat International Airport
- Engineering
 
Project Features
Client
					Polimeks Construction
				
			Key Quantities
| Stone Column | 98,500 m | 
| Jet Grout | 162,000 m | 
Project Duration
| Start Date | 01.03.2013 | 
| Finish Date | 01.02.2014 | 
| Duration | 11 Months | 
Location
Ashgabat, Turkmenistan