Warning: Undefined array key 0 in /home/kasktascom/public_html/wp-includes/meta.php on line 638
C&WP Topside Project | KASKTAŞ
  • 001

This project consists of the modernization and strengthening of quayside works; where petroleum platforms will be constructed. Ground improvement by stone column method was implemented under the unloading berth area; where extremely high loads were placed. In addition to 10,000 m of 820 mm diameter vertical and raked steel pipe piles, a total of 122,000 m of 800 to 1,000 mm diameter stone columns were installed by vibroreplacement technique.

Project Description

C&WP Topside Project

  • Engineering

Project Features

Client
Tekfen Construction
Key Quantities
Stone Column (with Vibroreplacement Technique) 122,000 m
Vertical and Raked Steel Pipe Pile (Vibrocompaction by Vibroflotation Technique) 10,000 m
Project Duration
Start Date 01.02.2003
Finish Date 01.01.2004
Duration 11 Months

Location

Baku, Azerbaijan

 

 

Gallery

Related Projects

Masar Project ST 06 Bored Pile Works

Masar Project ST...

Completed Projects Deep...
MASAR PROJECT PACKAGE A-B SHORING WORKS

MASAR PROJECT PACKAGE...

Asia Completed Projects...
NCMS TOWERS PROJECT

NCMS TOWERS PROJECT

Asia Completed Projects...
Jabal Al Ka’Aba Phase 3 Slope Stabilization Works

Jabal Al Ka’Aba...

Asia Completed Projects...