This project consists of the modernization and strengthening of quayside works; where petroleum platforms will be constructed. Ground improvement by stone column method was implemented under the unloading berth area; where extremely high loads were placed. In addition to 10,000 m of 820 mm diameter vertical and raked steel pipe piles, a total of 122,000 m of 800 to 1,000 mm diameter stone columns were installed by vibroreplacement technique.
Project Description
C&WP Topside Project
- Engineering
 
Project Features
Client
					Tekfen Construction
				
			Key Quantities
| Stone Column (with Vibroreplacement Technique) | 122,000 m | 
| Vertical and Raked Steel Pipe Pile (Vibrocompaction by Vibroflotation Technique) | 10,000 m | 
Project Duration
| Start Date | 01.02.2003 | 
| Finish Date | 01.01.2004 | 
| Duration | 11 Months | 
Location
Baku, Azerbaijan

                                




