In this project, where the employer is Sedef Gemi İnşaat, a total of 168,000 m Jet Grout Column and 35,000 m Bored Pile were installed in Tuzla Sedef Shipyard between 2005-2008.
Project Description
Tuzla Sedef Shipyard
- Engineering
 
Project Features
Client
					Sedef Gemi İnşaat
				
			Key Quantities
| Bored Pile | 35,000 m | 
| Jet Grout Column | 168,000 m | 
Project Duration
| Start Date | 01.04.2005 | 
| Finish Date | 01.12.2008 | 
| Duration | 45 Months | 
Location
Istanbul, Turkey

                                